Networking >> IPAM Project Page
Announcements
March 23, 2009 - System go live
The new IPAM system is now operational. DNS and DHCP services are working properly.
The IPAM web interface is now accessible to IPAM users.
HSC Units should have on-site support coverage on Monday, March 23 at 7:00am
March 22, 2009 - Cutover Sunday
Our HealthNet Bridge back up. Please call in to 273-8386 with your test results.
HSC Units should have on-site support coverage on Monday, March 23 at 7:00am
HSC Units New IPAM cutover, validation and testing, Sunday, March 22, 11:00am - ~1:30pm (Started DNS & DHCP testing)
IP Admin & Bluecat Consultant Old IPAM to New IPAM cutover, STARTED (DNS deployed, DHCP deployed)
Final Conversion Data, Data Errors, Orphans, HSC Statistics
March 16, 2009
HSC Units should have on-site support coverage on Monday, March 23 at 7:00am
HSC Units New IPAM cutover, validation and testing, Sunday, March 22, 11:00am - ~1:30pm
IP Admin & Bluecat Consultant Old IPAM to New IPAM cutover, Sunday, March 22, 9:00am -11:00am
End User Communication Template
Cutover Day Schedule, Sample Test Plan, Triage Procedures
Conference Bridge To Check In and Report Test Results - 273-8386
New registrations frozen - NOON on Thursday, March 19
IPAM Data Conversion Iteration 4 - Due 5:00pm, Tuesday, March 17
Data Conversion form for Iteration 4
Test of new Bluecat release revealed no show stoppers - March 12-13, 2009
Latest Conversion Data, Data Errors, Orphans, HSC Statistics
March 3, 2009
HSC Units New IPAM cutover validation and testing, Sunday, March 22, 11:00am - ~3:00pm
IP Admin & Bluecat Consultant Old IPAM-New IPAM cutover, Sunday, March 22, 9:00am -11:00am
New registrations frozen - COB Thursday, March 19
IPAM Data Conversion Iteration 4 - Due 5:00pm, Tuesday, March 17
Data Conversion form for Iteration 4
Test Bluecat Release at Shands/HSC Tue, March 10 - Monday, March 16
Sign up to help us test new release (Using the HSC Library training room and our IPAM training exercises)
Bluecat Code Release delayed until Monday, March 9
Latest Conversion Data, Data Errors, Orphans, HSC Statistics
February 17, 2009
New IPAM cutover tentatively re-scheduled for Sunday, March 22
New registrations frozen - COB Thursday, March 19
IPAM Data Conversion Iteration 4 - Due Tuesday, March 17
Test Bluecat Release at Shands/HSC Thursday, Feb. 26 - Monday, March 16
Bluecat Code Release due Wednesday, February 25
Current HSC Upload Data and Upload Exceptions
Orphans 3 (in process)
February 16, 2009
Data conversion form for iteration 4
Early de-registrations - look-up for unexpected loss of connection
HSC Upload Data and Upload Exceptions
Cutover - February 15, 2009 - Postponed until March 22, 2009
POSTPONEMENT INFORMATION
HSC Upload Data and Upload Exceptions
Early de-registrations
Cutover Day Schedule, Sample Test Plan, Triage Procedures
Conference Bridge To Check In and Report Test Results- temporarily disabled
Implementation Kit - February 11, 2009
End User Communication Template
Cutover Day Schedule, Sample Test Plan, Triage Procedures
Data Submission Status - February 5, 2009
Orphans version 2
Iteration 1 and 2 Error Reports
HSC Units and Devices Submission Status After Iteration 2
Submission date for third iteration - Close of Business, Tuesday, February 10
Data conversion form
Data Submission Status - February 2, 2009
Iteration 1 and 2 Error Reports
HSC Units and Devices Submission Status After Iteration 2
Orphans version 2 availability - TBD
Submission date for third iteration - tentatively Tuesday, February 10
Data conversion form
Data Submission Status - January 23, 2009
Orphans List Iteration 1
Submission date for second iteration - Thursday, 1/29/2009
Updated version of the data conversion form
Data Submission Status - January 14, 2009
The first iteration data submission has ended. Status for all Units
The 'orphans' list will be published here early next week
Second submission date will be announced early next week
IPAM User Training - January 12, 2009
IPAM User Training now available. Required prior to obtaining IPAM account.
Data Conversion Documents - December 9, 2008
Data conversion form due January 13, 2009
Data conversion instructions
Data conversion schedule
IPAM Implementatin Postponement:
Early Sunday morning, February 15, Gary Bennett, our IP Admin, was doing some final testing after all data were loaded. He found page refresh for basic users at 1-3 minutes. It appears to be due to the code that checks user permissions each time the user clicks on a MAC record or IP record request.
Bluecat software engineering will be releasing new code on Wednesday, February 25, 2009 that addresses this problem. Gary will install it as soon as he can after receiving the release, and the IPAM project team will commence testing at that time. If the problem is fixed, and if the IPAM project team does not uncover additonal serious issues, we will attempt to cut over to the new IPAM system on Sunday, March 22, 2009. We will change the cutover date from tentative to firm (or delayed again) no later than Friday, March 13, 2009.
Please continue to watch your email and this IPAM project web site for updates. We’ll do everything we can to keep you updated.
Schedule / Milestones
Milestone |
Assigned To: |
Tentative |
| Data Import Form and Instructions | Cebel | Complete |
| BlueCat IPAM Administrators Training | IPAM Project Team, Bluecat Networks | Complete |
| IPAM in Drupal | Jason | |
| De-registration of inactive devices | IP Administrator | complete |
| Device Reg Training for Units | Cebel, Perez, Unit ISMs | Complete - over 100 people trained |
| Publish IPAM Operation Web Site | Jason | TBD |
| Submission of Device inventory import file - 1st iteration | Unit ISMs | Complete - 100% of Units submitted |
| Publication of Inactive devices targeted for de-registration/review by Units/de-reg | Bennett/Ebel/ISMs | 1/26/09 - 1/31/09 - completed |
| De-registration of inactive devices | IP Administrator | 1/31/2009 - completed, ~37,000 devices deactivated |
| Publication of "orphaned devices" list | Bennett/Ebel | Completed and published |
| Submission of Device inventory import file (from orphaned list) - 2nd iteration | Unit ISMs | Thu 1/29/09 - 100% of Units submitted 12,111 devices |
| Update "orphaned devices" list | Bennett/Ebel | Completed and published |
| Bluecat Networks implementation engineer on-site for implementation planning, data upload and go-live support. | Bluecat Networks /Bennett | TBD |
| Submission of Device inventory import file (from orphaned list) - 3rd iteration | Unit ISMs | Tue 2/10/09 |
| Update "orphaned devices" list | Bennett/Ebel | Wed 2/12/09 |
| Final opportunity to register orphaned devices; manual registration in Proteus | Unit ISMs | Tentatively Sat 2/14/09 - Sun 2/15/09 |
| Walkthrough of cutover steps; final preparations & pre-prod testing | IPAM Project Team, Bluecat Networks | Fri 2/13/09 - Sat 2/14/09 |
| Cutover and production testing | IPAM Project Team, Bluecat Networks, Unit ISMs | Sun 2/15/09, 10:00am |
| Shands/HSC go live - heightened support | IPAM Project Team, Bluecat Networks, Unit ISMs | Mon 2/16/09 - until no longer needed |
Meeting Notes
2/28/2008 |
|
9/23/2008 |
|
Documentation
1/4/2009 |
|
3/26/2009 |
|
| Procedures, tasks and more information for IPAM users | |
12/8/2008 |
|
|
|
11/9/2007 |
|
|
|
11/19/2007 |
|
|
|
3/20/2008 |
|
9/19/2007 |
|
|
|
11/21/2008 |
|
2/13/2008 |
|
2/24/2008 |
|
|
|
2/24/2008 |
|
11/28/2007 |
|
|
|
12/8/2008 |
|
5/14/2008 |
|
|
|
11/21/2008 |
|
|
|
11/21/2008 |
|
Overview / Background
The IPAM project is a cross organizational project including Shands IS, HealthNet and the HSC Information Security Office (HSC ISO.) The result of the project will touch every computer on our HealthNet network. It involves the replacement of our current Shands homegrown device registration, DHCP and DNS services. The replacement solution is Bluecat Networks, Inc. Adonis and Proteus products. Adonis is the DHCP service and Proteus is the IP management interface. This project is not just a system replacement. The project includes a process redesign of the device regististration life cycle.
Objectives
This project seeks to achieve the following key objectives:
- Manage public IP address space
- Establish an institutional respository containing the identification, support and security ownership for every device on the network
- Provide Units and HealthNet with more visibility regarding network device activity to improve support
- Distribute control of DHCP parameters to the HSC Units
- Establish network security zones to limit the surface area accessible from the Internet
- Improve
information security incident response and handling
Project Team
| Avi Baumstein, HSC ISO | David Huelsman, HSC ISO |
| Gary Bennett, Shands IS | Mark Kovacic, Shands ISO |
| Duane Callahan, Shands IS | Tom Livoti, HealthNet |
| Philip Chase, HSC PHHP | Tim Nance, Shands ISO |
| Jason DeLeon, HealthNet | Fabian Perez, HSC ISO |
| Colleen Ebel, HSC ISO | Josh Viessman, HSC CoVM |