Networking >> IPAM Project Page


Announcements

March 23, 2009 - System go live
The new IPAM system is now operational. DNS and DHCP services are working properly.
The IPAM web interface is now accessible to IPAM users.
HSC Units should have on-site support coverage on Monday, March 23 at 7:00am

March 22, 2009 - Cutover Sunday
Our HealthNet Bridge back up. Please call in to 273-8386 with your test results.
HSC Units should have on-site support coverage on Monday, March 23 at 7:00am
HSC Units New IPAM cutover, validation and testing, Sunday, March 22, 11:00am - ~1:30pm (Started DNS & DHCP testing)
IP Admin & Bluecat Consultant Old IPAM to New IPAM cutover, STARTED (DNS deployed, DHCP deployed)
Final Conversion Data, Data Errors, Orphans, HSC Statistics

March 16, 2009
HSC Units should have on-site support coverage on Monday, March 23 at 7:00am
HSC Units New IPAM cutover, validation and testing, Sunday, March 22, 11:00am - ~1:30pm
IP Admin & Bluecat Consultant Old IPAM to New IPAM cutover, Sunday, March 22, 9:00am -11:00am
End User Communication Template
Cutover Day Schedule, Sample Test Plan, Triage Procedures
Conference Bridge To Check In and Report Test Results - 273-8386
New registrations frozen - NOON on Thursday, March 19
IPAM Data Conversion Iteration 4 - Due 5:00pm, Tuesday, March 17
Data Conversion form for Iteration 4
Test of new Bluecat release revealed no show stoppers - March 12-13, 2009
Latest Conversion Data, Data Errors, Orphans, HSC Statistics

March 3, 2009
HSC Units New IPAM cutover validation and testing, Sunday, March 22, 11:00am - ~3:00pm
IP Admin & Bluecat Consultant Old IPAM-New IPAM cutover, Sunday, March 22, 9:00am -11:00am
New registrations frozen - COB Thursday, March 19
IPAM Data Conversion Iteration 4 - Due 5:00pm, Tuesday, March 17
Data Conversion form for Iteration 4
Test Bluecat Release at Shands/HSC Tue, March 10 - Monday, March 16
Sign up to help us test new release (Using the HSC Library training room and our IPAM training exercises)
Bluecat Code Release delayed until Monday, March 9
Latest Conversion Data, Data Errors, Orphans, HSC Statistics

February 17, 2009
New IPAM cutover tentatively re-scheduled for Sunday, March 22
New registrations frozen - COB Thursday, March 19
IPAM Data Conversion Iteration 4 - Due Tuesday, March 17
Test Bluecat Release at Shands/HSC Thursday, Feb. 26 - Monday, March 16
Bluecat Code Release due Wednesday, February 25
Current HSC Upload Data and Upload Exceptions
Orphans 3 (in process)

February 16, 2009
Data conversion form for iteration 4
Early de-registrations - look-up for unexpected loss of connection
HSC Upload Data and Upload Exceptions

Cutover - February 15, 2009 - Postponed until March 22, 2009
POSTPONEMENT INFORMATION
HSC Upload Data and Upload Exceptions
Early de-registrations
Cutover Day Schedule, Sample Test Plan, Triage Procedures
Conference Bridge To Check In and Report Test Results- temporarily disabled

Implementation Kit - February 11, 2009
End User Communication Template
Cutover Day Schedule, Sample Test Plan, Triage Procedures

Data Submission Status - February 5, 2009
Orphans version 2
Iteration 1 and 2 Error Reports

HSC Units and Devices Submission Status After Iteration 2
Submission date for third iteration - Close of Business, Tuesday, February 10
Data conversion form

Data Submission Status - February 2, 2009
Iteration 1 and 2 Error Reports
HSC Units and Devices Submission Status After Iteration 2
Orphans version 2 availability - TBD
Submission date for third iteration - tentatively Tuesday, February 10
Data conversion form

Data Submission Status - January 23, 2009
Orphans List Iteration 1
Submission date for second iteration - Thursday, 1/29/2009
Updated version of the data conversion form

Data Submission Status - January 14, 2009
The first iteration data submission has ended. Status for all Units
The 'orphans' list will be published here early next week
Second submission date will be announced early next week

IPAM User Training - January 12, 2009
IPAM User Training now available. Required prior to obtaining IPAM account.

Data Conversion Documents - December 9, 2008
Data conversion form due January 13, 2009
Data conversion instructions
Data conversion schedule

IPAM Implementatin Postponement:
Early Sunday morning, February 15, Gary Bennett, our IP Admin, was doing some final testing after all data were loaded. He found page refresh for basic users at 1-3 minutes. It appears to be due to the code that checks user permissions each time the user clicks on a MAC record or IP record request.  

Bluecat software engineering will be releasing new code on Wednesday, February 25, 2009 that addresses this problem. Gary will install it as soon as he can after receiving the release, and the IPAM project team will commence testing at that time. If the problem is fixed, and if the IPAM project team does not uncover additonal serious issues, we will attempt to cut over to the new IPAM system on Sunday, March 22, 2009. We will change the cutover date from tentative to firm (or delayed again) no later than Friday, March 13, 2009.

Please continue to watch your email and this IPAM project web site for updates.   We’ll do everything we can to keep you updated.

Schedule / Milestones

Milestone
Assigned To:
Tentative
Data Import Form and Instructions Cebel Complete
BlueCat IPAM Administrators Training IPAM Project Team, Bluecat Networks Complete
IPAM in Drupal Jason  
De-registration of inactive devices IP Administrator complete
Device Reg Training for Units Cebel, Perez, Unit ISMs Complete - over 100 people trained
Publish IPAM Operation Web Site Jason TBD
Submission of Device inventory import file - 1st iteration Unit ISMs Complete - 100% of Units submitted
Publication of Inactive devices targeted for de-registration/review by Units/de-reg Bennett/Ebel/ISMs 1/26/09 - 1/31/09 - completed
De-registration of inactive devices IP Administrator 1/31/2009 - completed, ~37,000 devices deactivated
Publication of "orphaned devices" list Bennett/Ebel Completed and published
Submission of Device inventory import file (from orphaned list) - 2nd iteration Unit ISMs Thu 1/29/09 - 100% of Units submitted 12,111 devices
Update "orphaned devices" list Bennett/Ebel Completed and published
Bluecat Networks implementation engineer on-site for implementation planning, data upload and go-live support. Bluecat Networks /Bennett TBD
Submission of Device inventory import file (from orphaned list) - 3rd iteration Unit ISMs Tue 2/10/09
Update "orphaned devices" list Bennett/Ebel Wed 2/12/09
Final opportunity to register orphaned devices; manual registration in Proteus Unit ISMs Tentatively Sat 2/14/09 - Sun 2/15/09
Walkthrough of cutover steps; final preparations & pre-prod testing IPAM Project Team, Bluecat Networks Fri 2/13/09 - Sat 2/14/09
Cutover and production testing IPAM Project Team, Bluecat Networks, Unit ISMs Sun 2/15/09, 10:00am
Shands/HSC go live - heightened support IPAM Project Team, Bluecat Networks, Unit ISMs Mon 2/16/09 - until no longer needed
     


back to top

Meeting Notes

 

2/28/2008
 
9/23/2008
 

back to top

Documentation

1/4/2009
3/26/2009
Procedures, tasks and more information for IPAM users
12/8/2008

Device Registration Data Conversion Instructions

11/9/2007

IPAM System Needs and Requirements

11/19/2007

HSC Information Security IP Migration - Existing Use & New IP Space

3/20/2008
 
9/19/2007

To bring the following three projects together: 1) IP Administration Application Replacement and Registration Process Improvement, 2)IP Allocation Model, 3) Network Security Zones

back to top

11/21/2008
 
2/13/2008
 
2/24/2008

Documents functionality of the Proteus API for controlling the Proteus IPAM apppliance & offers instructions on its implementation and usage.

2/24/2008
 
11/28/2007

Description of the current, diverse environment with a prioritization of the requirements for an extensible IPAM system

back to top

12/8/2008

 

5/14/2008

Describes the functionality of the Proteus IPAM Appliance by BlueCat Networks and offers instructions on its implementation and usage.

11/21/2008

UF HSC Device Registration Data - Conversion and Re-registration Plan

11/21/2008
 
   
 

Overview / Background 

The IPAM project is a cross organizational project including Shands IS, HealthNet and the HSC Information Security Office (HSC ISO.) The result of the project will touch every computer on our HealthNet network. It involves the replacement of our current Shands homegrown device registration, DHCP and DNS services. The replacement solution is Bluecat Networks, Inc. Adonis and Proteus products. Adonis is the DHCP service and Proteus is the IP management interface. This project is not just a system replacement. The project includes a process redesign of the device regististration life cycle.

Objectives
This project seeks to achieve the following key objectives:

  1. Manage public IP address space
  2. Establish an institutional respository containing the identification, support and security ownership for every device on the network
  3. Provide Units and HealthNet with more visibility regarding network device activity to improve support
  4. Distribute control of DHCP parameters to the HSC Units
  5. Establish network security zones to limit the surface area accessible from the Internet
  6. Improve information security incident response and handling

Project Team

Avi Baumstein, HSC ISO David Huelsman, HSC ISO
Gary Bennett, Shands IS Mark Kovacic, Shands ISO
Duane Callahan, Shands IS Tom Livoti, HealthNet
Philip Chase, HSC PHHP Tim Nance, Shands ISO
Jason DeLeon, HealthNet Fabian Perez, HSC ISO
Colleen Ebel, HSC ISO Josh Viessman, HSC CoVM



back to top

 

Mission, Staff/Contact Us, HN Policies, HN Public Service Commission, HN Forum, Major Projects

User Guide, Service Request, Report Trouble, FAQs

User Guide, Service Request, Report Trouble, FAQs

Overview, Purchasing HealthNet Services, Making Payments to HealthNet, Past Due Accounts, FAQs

FAQs, Report Trouble